Physical Progress as on 31st Oct. 2019

Contract PackagesCumulative progress (%) as of previous monthCumulative progress (%) as of 31.10.2019
MC-1 (including Hydro-Mechanical works)

69.6869.68
MC-2 (including Hydro-Mechanical works)

100 100
MC-3 (including Hydro-Mechanical works)

97.4797.60
Electro-Mechanical works91.5591.92
Transmission Line99.2799.27
Total





86.1986.26