Physical Progress as on 31st August, 2019

Contract PackagesCumulative progress (%) as of previous monthCumulative progress (%) as of 31.08.2019
MC-1 (including Hydro-Mechanical works)

68.9169.68
MC-2 (including Hydro-Mechanical works)

100 100
MC-3 (including Hydro-Mechanical works)

97.2597.32
Electro-Mechanical works90.1991.38
Transmission Line99.1699.27
Total





85.6486.14