Physical Progress as on 31st July, 2019

Contract PackagesCumulative progress (%) as of previous monthCumulative progress (%) as of 31.07.2019
MC-1 (including Hydro-Mechanical works)

68.9168.91
MC-2 (including Hydro-Mechanical works)

100 100
MC-3 (including Hydro-Mechanical works)

97.1197.25
Electro-Mechanical works89.5090.19
Transmission Line99.1699.16
Total





85.5185.64